Project Name :
The Rama IV Bridge
Location :
Nonthaburi Province
Client :
Department of Rural Roads (DRR)
Project Cost :
1,511.72 million Baht (for bridge and east - west connecting road (Contract 1) only)
Project Duration :
See below
Project Description :
Bridge type: Prestressed concrete box-girder bridge
Vertical clearance: 5.60 m.
Bridge length: 278.00 m. (main bridge 134 m., viaduct 72 m. on each side of Nonthaburi
No. of traffic lane: 6 traffic lanes
Bridge width: 40.00 m.
Main Performance :
- Feasibility study, preliminary design and preliminary cost estimation (June 1993 - January 1994)
- Detailed design, preparation of tender documents and cost estimation (Part 1: October 1994 – November 1995 and Part 2: October 1996 – February 1997)
- Property survey (Part 1: November 1998 – April 1999 and Part 2: July 1999 – February 2000).