Project Name :
The Increment of Rail Efficiency and Capacity from Hua Mak-Chachoengsao-Si Racha and Double Track Railway from Si Racha-Map Ta Phut
Location :
Bangkok-Chachoengsao-Chon Buri and Chon Buri-Rayong Provinces
Client :
State Railway of Thailand (SRT)
Project Cost :
- million Baht
Project Duration :
October 2018 – May 2019
Project Description :
- Improve the existing railway
- Improve the signaling and telecommunication system
- Solve the level crossing problems from Hua Mak-Si Racha Junction Station for a total length of 115 km.
- Construct additional railway from Hua Mak-Chachoengsao for a total length of 46 km.
- Construct double-track railways from Si Racha Junction-Khao Chi Chan Junction-Map Ta Phut and from Khao Chi Chan Junction-Sattahip
- construct chord line at Si Racha Junction and Khao Chi Chan Junction for a total length of 85 km.
Main Performance :
Part 1 Review the detailed design, review the economic and financial analysis, review the construction cost and prepare the tender documents of commuter train and long distance train connecting mass rapid transit system in Bangkok Metropolitan Region from Hua Mak-Chachoengsao.
Part 2 Feasibility study, detailed design and preparation of environmental impact assessment report for double-track railway from Hua Mak-Chachoengsao-Si Racha Junction Station-Map Ta Phut.