Project Name :
The Expressway Connecting Si Rat Expressway, Portion D to Chaturathit Road, Section Kor
Location :
Bangkok Metropolis
Client :
Bangkok Expressway Public Company Limited
Project Cost :
200 million Baht
Project Duration :
February 2013 – May 2014
Project Description :
- 1-lane ramp with the total length of 550 m.
- 4-lane toll collection plaza together with 4 toll booths.
- Walkway of 1.5 m. wide with the total length of 57 m.
- Improvement of the elevated toll surveillance building
- Installation of electronic toll collection system and traffic control system.
Main Performance :
Detailed design, cost estimation and construction supervision.