DESIGN AND CONSTRUCTION SUPERVISION FOR THE SKYWALKWAY LINKING THE BRT AND BTS AT SATHORN INTERSECTION

 

 

Detailed Narrative Descriptive of Project :
The Lane and Intersection Improvement Works for Bus Rapid Transit (BRT) Project, Route Chong Nonsi – Rachapruk, have the detailed narrative descriptive works as follows;
·      The construction of elevated steel structure platform for the Connecting Walkway between Bus Rapid Transit (BRT) Station andBTS Station over Sathorn – Narathiwat Intersection, approximately 36 meters width x 55 meters long.
·      The expansion of existing pedestrian bridges, Northern and Southern side, over Narathiwat road, approximately 57 meters long each.
·      The construction of 4 stairs along the North Sathorn and South Sathorn roads.

 
 
Detailed Description of Actual Services provided :
 
The management and supervision for the civil infrastructure construction of the BRT: Chong Nonsi – Rachapruk. The services are also included the following works;
·      Review and check the construction drawings, specifications, and all contract documents.
·      Review and approve the construction schedule proposed by the contractor.
·      Review and approve the as-built drawings proposed by the contractor.
·      Supervise for the site construction’s problems and solutions.
·      Control the construction quality conforming to the drawings and specifications.
·      Consulting and recommend the practical construction standards.
·      Certify the material testing and quantity of work done according to the contract.
·      Certify the completion of work.
·      Manage and supervise defect works during the 2 years maintenance period.