INVESTIGATION OF CAPACITY CONSTRAINTS AND DETERMINATION OF THE NEED FOR TRACK DOUBLING FOR SRT NETWORK (TDSN)

   
  • To identify the optimal order in which track doubling of discrete line sections should be implemented.
  • To determine the timing of the track doubling for each line section.
  • To make justify on going tripling/doubling project and prepare 30 years Master Plan at 5 years interval.
  • Preliminary engineering design and costs estimate of track doubling projects in the first 5 years plan.
  • Economic and Financial evaluation.
  • Initial environmental study.

Detailed Description of Actual Services provided :

  • Description f existing railway system.
  • Estimation of future rail travel demand.
  • Railway performance options analysis.
  • Evaluation options.
  • Master plan preparation.
  • Preliminary engineering design.
  • Cost estimate.
  • Economic and financial evaluation.
  • Initial environmental study.
  • Project implementation plan.