TRACK DOUBLING FOR THE EAST COAST LINE CHACHOENGSAO – KLONG SIP KAO-KAENG KHOI (CKK)

   
 

The Project Track Doubling for East Coast Line Chachoengsao-Klong Sip Kao-Kaeng Khoi has the major works as follows;

  1. Construction of Track Doubling Chachoengsao-Klong Sip Kao-Kaeng Khoi approximated distance 106 k.m.
  2. Construction of Chord Line 3 locations approximated distance 6 k.m. at Chachoengsao, Kaeng Khoi and Ban Phachi.
  3. Installation of Signalling and Telecommunication System for Track Doubling as mentioned in (1) and (2)
  4. Preparation and Land Acquisition for the construction of Chord Line.

Detailed Description of Actual Services provided :

  • Study and Review the Feasibility Study in 2001, the EIA report in 1998, then Improve the information conforming to the present situation.
  • Prepare Feasibility Study Report.
  • Prepare Detailed Design Drawings, Cost Estimate, and Tender Document ready for tender.
  • Prepare EIA Report, improving and revising according to the concerned authorities’ comment, including the public hearing following the government 2005 regulations.